How many working days in year 2006?
Here is the detail of the calculation:
Because 2006 is not a leap year, it has 365 days.
Let's remove 52 saturdays and 52 sundays. It remains 261 days.
Now, let's remove 5 public holidays that do not fall during a weekend and we obtain 256 working days in 2006.
Here is the list of these 5 public holidays:
1. פסח : Thursday, 13 April, 2006
2. שביעי של פסח : Wednesday, 19 April, 2006
3. יום העצמאות : Wednesday, 3 May, 2006
4. ראש השנה : Sunday, 24 September, 2006
5. יום כיפור : Monday, 2 October, 2006
And here are the 4 public holidays falling on a weekend:
1. שבועות : Friday, 2 June, 2006
2. ראש השנה : Saturday, 23 September, 2006
3. סוכות : Saturday, 7 October, 2006
4. שמחת תורה/שמיני עצרת : Saturday, 14 October, 2006